https://issues.apache.org/jira/browse/OFBIZ-4853?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel ]
Pierre Smits reassigned OFBIZ-4853:
-----------------------------------
Assignee: Pierre Smits (was: Jacques Le Roux)
> Project resource overview doesn't show the resources with a thru-date before the current date.
> ----------------------------------------------------------------------------------------------
>
> Key: OFBIZ-4853
> URL:
https://issues.apache.org/jira/browse/OFBIZ-4853> Project: OFBiz
> Issue Type: Bug
> Components: projectmgr
> Affects Versions: Release 10.04, Release 11.04.01, Release Branch 11.04, Trunk
> Reporter: Pierre Smits
> Assignee: Pierre Smits
> Fix For: Trunk
>
> Attachments: OFBIZ-4853-project-resources.patch
>
> Original Estimate: 0.5h
> Remaining Estimate: 0.5h
>
> When a project manager expires the assignment of a resource by clicking the delete button in the Project Resources overview the resource is deleted from the overview. It should be that the resource is still shown in the overview with the tru-date visible.
> Otherwise there will be a discrepancy between the overview of resources of the project and the project dashboard.
> The name of the button is also wrong. It should state 'expire' not 'delete'.
--
This message was sent by Atlassian JIRA